Client: GTCI Date: July – December 2019
Project: Complete mechanical installation throughout the main school building.
Location: Gravesend, Kent
The Project
The school required substantial work following a ceiling collapse which closed part of the school.
Our Involvement
Full installation of heating system pipework feeding low surface temperature radiators and air handling units. Alterations to the plant room to accommodate the new system. Full installation of domestic pipework feeding new toilet rooms and kitchens.
Challenges
Despite the huge amount of work involved, the first phase needed to be completed during the 6 week summer holiday to ensure the school was ready for when the children came back to school, to minimise disruption to classes.
Key Achievements
All deadlines were stuck to and finished ahead of time. Job was signed off with no issues.